BHA Operations Tab
Daily Operations Report > Drillstrings Section
To properly analyze BHA performance, operational information is needed over the depth interval of the BHA Run. This information can be recorded in the BHA Operations tab.
This section contains a Detail Spreadsheet which records each operation of the selected BHA in the BHA Run Summary table.
Copy From Previous BHA Operation Button
The Copy From Previous BHA Operation button copies a previously entered BHA Operation for the current BHA Run into the BHA Operations spreadsheet. When this button is selected a dialog appears listing all BHA Operations entered for the current BHA Run. Select the BHA Operation to be copied and click OK. Edit the operation to correctly reflect the current Operations parameters.
Drill Mode
The Drill Mode picklist directly affects Progress Summary calculations appearing in the Summary Tab.
Select Rotating to identify the BHA Operation as rotating time. When Rotating is selected the operation's Footage and Drilling Hours are used in the Total Rotating Footage and Total Rotating hours calculations.
Select Sliding to identify the BHA Operation as sliding time. When Sliding is selected the operation's Footage and Drilling Hours are used in the Total Sliding Footage and Total Sliding hours calculations.
Directional Parameters
MD
Measured Depth (MD) is the depth for the operations parameters. The MD and the Time parameters define where and when the parameters were recorded.
TVD
The True Vertical Depth (TVD) field is a calculated field. When the first row is added to the BHA Operations table, the TVD field is calculated based on MD entered interpolated from survey starting data entered in the Survey section.
String Operation Parameters
Drag
The Drag field is calculated as follows: Drag = String Weight Up - String Weight Rotating.
Progress Parameters
Footage
Footage is the amount of hole drilled since the BHA operation. This field is calculated as follows:
Footage = MD (of current BHA operation) - MD (of previous BHA operation)
ROP
Rate of Progress (ROP) is the progress rate calculated using Progress BHA operation. This field is calculated as follows:
ROP = Footage / Drilling Hours
Dull Mode
Dull Mode identifies for which type of operation the drilling parameters are recorded.
Cum Drilling
The Cumulative Drilling (hours) field is calculated as follows:
Cum Drilling = ∑ Drilling Hours for all BHA Operations for the current Drillstring
Cum Circulating
The Cumulative Circulating (hours) field is calculated as follows:
Cum Circulating = ∑ Circulating Hours for all BHA Operations for the current Drillstring
Cum String
The Cumulative String (hours) field is the sum of the of the Cumulative Drilling hours and Cumulative Circulating hours.
Related Topics